Road and Bridge reports 1.16 miles completed, multiple projects in progress

Jul 17, 2026

County Road & Bridge staff reported 1.16 miles completed and about 13.24 miles in progress as of June 12, 2023; the court approved a change order adding 2,365 square yards of chip-seal work and discussed mapping discrepancies with TxDOT.

The full story

Road & Bridge Director Mr Davis summarized the department's June 12 construction report and told the court the department had "completed 1.16 miles" with 13.242 miles in progress on multiple county roads, including Boggy Road, Fern Lake cutoff, Galilee Road and Simmons Road.