Santa Rosa ISD bond update: $2.495M remains; Hog Barn schematic advances amid sprinkler concerns

Oct 20, 2025

Project manager presented the Oct. 2025 bond allocation report showing a remaining bond balance of $2,495,091.18 and schematic design work underway for LED lighting, intercom, fire alarm and Hog Barn renovations; structural constraints for installing sprinklers on a wood lamella roof were highlighted.

The full story

Project Manager Ernie Villarreal presented the board's bond-allocation update and preliminary designs at the Oct. 20 meeting.

The packet lists detailed budgets by project and a reported "Remaining Bond Balance $ 2,495,091.18." Villarreal and the project team described schematic-design progress: LED lighting and intercom upgrades were roughly 80% complete; fire alarm schematic work was similarly advanced; and early work on gym fire-suppression design is ongoing. The team noted a structural review is underway because an older lamella wood roof may not be able to carry the weight of fire-sprinkler piping, which could limit sprinkler installation in Chepe Gym.

The board also reviewed schematic floor plans and fencing/site-work details for the Ag Shop Hog Barn renovation; GMS Architects and Ethos Engineering were identified in the materials as providing design and task-order services. The bond report showed allocations across campus projects (Barrera Elementary, a CTE/Early College building, athletic facilities and contingencies) and itemized allocated costs and remaining balances for each line.