Council approves $195,073.25 change order for Shared Use Path Phase 2

Dec 10, 2024

Council approved a $195,073.25 change order for the Shared Use Path Phase 2 after engineers reported right-of-way limits prevented a ditch adjacent to the path; council also raised concerns about parking on the path and why Phase 1 did not extend to the road in concrete.

The full story

The Fruitland City Council approved a $195,073.25 change order for Phase 2 of the Shared Use Path project during its Dec. 10 meeting. Councilmember Painter moved to approve the change order; Hogan seconded and the motion passed unanimously among the four members present.