CDD updates drainage work; crews to remove, replace trees and finish by end of July
Jun 23, 2026
Jun 23, 2026
District Engineer Charlie Krebs told the Board all four drainage sites are under construction; pipe installation and grading schedules were given, with 12 trees in Palmetto Dunes to be removed/replaced and six Cabbage Palms in Oak Run to be replanted. Some repairs will be charged to contingency.
The full story
District Engineer Charlie Krebs reported June 23 that all four drainage improvement sites within River Ridge are under active construction, with cleared sites, silt fences installed and pipe installation scheduled in Oak Run the week of June 29. He said Palmetto Dunes is expected to be completed by the end of the week and the overall project is expected to finish by the end of July.