Public works told council crews have completed thousands of pounds of sandbag/headwall work and billed about $163,000 in work since January 2025; about 31–36 headwalls remain and TxDOT replaced a Mill Creek stop sign with a larger, more reflective one.

The full story

Mr. Marshall (speaker 6) updated council on public-works activity, saying crews have been focused on headwalls and culverts and have made considerable progress. He reported that crews placed "2 10 bags in 2 days" and that the department has issued about 83 work orders since January 2025 — roughly 14 per month — and has billed approximately $163,000 for that work.