Committee: CBC approves eligibility for inclusive playground; scope and RFP next
Aug 5, 2026
Aug 5, 2026
Committee members reported CBC approval of eligibility for an inclusive-playground project and agreed the next steps are a written scope from consultant Larry, an updated CPC application (Phase 1 engineering $25,000) and a likely RFP for procurement; full project estimates discussed ranged roughly $450,000–$505,100.
The full story
Committee member reported that the CBC has approved the project's eligibility and that the town manager will take the lead on submitting the application. Members emphasized that the application currently reflects a Phase 1 engineering request of $25,000 while the full project budget remains an estimate and will be revised after a detailed scope and pricing from the consultant (Larry).