Boiler replacement contract adjusted; final contract $2.81 million after net deduct

Jan 13, 2026

Commissioners approved Change Order #3 with Bodie Mechanical Services for the county Boiler Replacement Project, producing a net deduct of $6,963.50 and a final contract value of $2,809,715.50.

The full story

Phil Johnson presented Change Order #3 to the contract with Bodie Mechanical Services, Inc. for the Boiler Replacement Project that covers multiple county structures. Phil said the change order includes several additions and subtractions that result in a net deduct of $6,963.50. The final contract cost after the change order is listed as $2,809,715.50. The board approved the change order on a 3-0 vote.