Collier County public utilities reports $1B Northeast facilities program remains on schedule

Jul 14, 2026

Public Utilities reported progress on the Northeast facilities program: interim wastewater plant (1.5M gpd), potable/irrigation storage tanks, deep injection and production wells, and engineering underway for 10 MGD water and 6 MGD wastewater plants. Staff asked for board acceptance of the update and the board approved the report.

The full story

Matt McClain, interim department head for Collier County Public Utilities, told commissioners the Northeast facilities program has advanced key components over the past year, including pipeline transmission mains, drilling of production wells into the Lower Tamiami Aquifer, an interim 1.5 million‑gallon‑per‑day wastewater treatment facility, and two 7.5‑million‑gallon storage tanks at the site.

"Financially, the program's updated estimated rough order of magnitude cost now exceeds $1,000,000,000," McClain said, citing inflation and construction cost increases. Staff told the board the project remains within scope and on schedule; commissioners asked clarifying questions about capacity integration with existing plants and about the phased delivery and funding strategy (bonds, commercial paper, impact fees). The board voted to accept the program update.

Written with AI from the event video and transcript. Check it against the source ↓