Design team: Lincoln County Commons can meet master plan but costs exceed budget by ~$6M

Oct 7, 2026

County project team presented revised master‑plan renderings and a contractor estimate of about $36 million in construction value — roughly $6 million above the county’s $30 million target — and outlined value‑engineering options including a smaller multipurpose building or alternative roof materials.

The full story

Design and construction representatives told the commission the Lincoln County Commons master plan satisfies program goals but early estimates put construction at about $36,000,000 — roughly $6,000,000 above the county's target budget.