Plainfield garage solar array produced 9.16 MWh; MERP grant deadlines and RFPs discussed

Aug 24, 2026

Energy Coordinator Bob Atchinson reported the town garage solar array has generated 9.16 MWh since commissioning and noted MERP grant contracting deadlines (Sept. 30, 2026); RFQs/RFPs were issued for wastewater solar and weatherization/HVAC work.

The full story

Energy Coordinator Bob Atchinson reported the Town Garage solar array—commissioned May 28, 2026 with MERP grant funding—has generated 9.16 MWh (9,160 kWh) to date and that staff are working with VLCT on IRS elective pay rebate processes.