Preschool construction delayed; board approves change orders as completion dates shift

Oct 22, 2024

Architects reported the Clark County preschool is more than 80% complete but tracked weather days and missed subcontractor milestones shifted substantial completion to Jan. 15 and final completion to Feb. 14; the board approved two change orders and discussed schedule and budget implications.

The full story

The Clark County school board heard a construction update on the new preschool and approved two contractor change orders after architects said weather days and missed milestones have pushed the schedule.