Company: project will interconnect to EKPC/PJM; no sales contracts signed yet

Oct 7, 2026

Company officials said the proposed 53 MW solar farm will interconnect to EKPC and the PJM regional transmission operator, that generated power flows to the nearest load, and that no offtake contracts were finalized at the time of the hearing.

The full story

Board members asked whether electricity from the proposed solar farm would serve local customers or be exported. Rob Riley (Silicon Ranch) said the project interconnects through EKPC and PJM and that, as he described it, "the power for... from this project will serve the closest load." He also said the company had not yet executed contracts for the sale of electricity and would seek to ensure all interconnection and permit requirements were met before marketing the project.