Connector project delayed after electrical load testing, board reviews gas‑line relocation options
Sep 17, 2024
District staff said electrical demand‑metering will delay the connector bid by about a month; the board reviewed three gas‑line relocation options and tentatively favored a sidewalk reroute with an estimated incremental cost of roughly $15,000 pending asbestos testing and refined estimates.
The full story
District facilities staff told the board that recent field work uncovered unbalanced demand loads in panels for the planned connector project and that the electrical engineer will need to set demand meters on panels for 30 days to finalize load calculations, delaying the bid timeline by an estimated four to five weeks.