Engineering office reports progress on AMD phases, Chub Run and Phase IV work

Feb 24, 2026

Staff reported milestones on multiple engineering projects: Phase 1 AMD administrative items, Phase 2 right-of-way progress (30 of 34 ROWs secured), Chub Run bid-opening moved to March 10, 2026, and Phase IV awaiting contractor remobilization.

The full story

Engineering staff updated council on multiple infrastructure projects. For Phase 1 AMD they presented Change Order 4, an Engineering Amendment 2 and a Notice of Acceptability. On Phase 2 AMD, staff said 30 of 34 rights-of-way (ROWs) are secured and they continue to work on ROWs for two businesses, one utility and one resident while the DOH permit is under review; tree felling and a to-bid meeting with AML were also noted.