District construction updates: CTE progress, stadium lights and multiple school projects noted

Feb 6, 2026

Officials reported progress on the CTE facility (switchgear connections, sprinkler and MEP work, exterior panels), ongoing renovations at multiple schools, new stadium lights at North Side High School and scheduling impacts from recent snow; board members praised the pace and discussed walkthrough timing.

The full story

Mr. Todd (construction updates) briefed the board on major and minor construction projects across the district. For the Career and Technical Education (CTE) facility, staff reported that temporary heat keeps interior work moving, site work was slowed by snow, curbs and gutters and the drill pad concrete were completed, the transformer and primary wires are in place, GRDs (grilles, registers and diffusers) were installed and the fire pump and sprinkler risers are finished; Area A has exterior metal panels and low-voltage wiring in place and Areas B and C advanced with mezzanines, gypsum board and MEP systems.

Free newsletter

Sign up to keep reading.

Your free newsletter brings you what your city council, county, and school board discussed and decided.

or
Already have an account? Sign in