Construction update: Colgate and Pilgrim progress; Pilgrim soils plan could keep 5–6,000 cubic yards on-site

Oct 8, 2025

Project managers reported Colgate High progress (drum-rock demolition complete; steel erection expected in December) and a Pilgrim soils remediation approach that may cap and retain 5–6,000 cubic yards on-site pending verification; short-term remedial action plan expected imminently.

The full story

Project staff updated the committee on progress at several high-school sites and provided soil-remediation options for Pilgrim.