Committee approves multiple change orders for Rogers project, directs design work for wider bus loop

Feb 3, 2026

The committee approved several owner‑contingency change orders totaling hundreds of thousands of dollars for the Rogers site, including safety and accessibility work, and asked staff and consultants to develop a full design and cost estimate for a proposed 3‑foot bus‑loop widening.

The full story

The committee overseeing the Rogers construction project approved a series of change orders on Monday that use owner and construction contingency funds to address safety, accessibility and operational needs, and directed staff to develop a full design and cost estimate for a proposed widening of the new bus loop.