Council approves pay application and change orders as Palm View fire station advances
Apr 22, 2026
Apr 22, 2026
Council approved payout No. 2 to Kimber 1985 LLC for March work on the new fire-station project, accepted a net credit in Change Order No.1 and approved add-back change directives totaling $460,083 for millwork, electrical/CCTV/fire alarm coordination and a roof upgrade; staff said retainage is 5%.
The full story
Construction manager Josh Surdivarano reported to council that pay application No. 2 for Kimber 1985 LLC covered work completed in March—foundation work, steel and CMU deliveries, site utilities and materials—and staff recommended approval.