Board reviews drainage improvements; Change Order #2 for $6,353.12 discussed
Jul 28, 2026
Jul 28, 2026
District engineers updated the Board on drainage projects across Turnberry, Palmetto Dunes, Sound III and Oak Run; a Change Order #2 for $6,353.12 was discussed and an additional per-unit change order will be submitted.
The full story
District Engineer Charlie Krebs and Mr. Eric Long briefed the Board on ongoing drainage improvements. Krebs said Clarke Construction is completing much of the work, with Turnberry nearly finished and Palmetto Dunes and Sound III completed (sod replaced and trees installed). Oak Run (Lakes 8) was being sodded but rain had delayed progress and standing water was reported; silt fences are in place.