Town engineer: replacements would require MDE construction permit, rebuild would not
Dec 4, 2024
Dec 4, 2024
Town Engineer Jason Lytle told the council the rebuild option for the influent screen would not require an MDE construction permit, while either replacement option would. That permit difference was cited as a material factor in council deliberations.
The full story
Town Engineer Jason Lytle told the Trappe Town Council at its Dec. 4 workshop that the town would not need an MDE construction permit if it chose the rebuild option for the influent screen but would require a permit for either replacement option.