Back Creek dredging project fully funded; Army Corps schedule targets 2029 construction

Oct 7, 2026

York County reported federal and nonfederal funding secured for a Back Creek dredging project: roughly $5.0 million federal, $1.4 million nonfederal (county), with the final ~$402,000 covered by a VMRC waterways grant; Army Corps condition surveys begin in early 2027 and construction bidding is planned for 2028 with work in 2029.

The full story

County staff and partner agencies updated the board on Oct. 6 about a long‑running dredging and navigation project for Back Creek that now appears fully funded. Staff described the project scope, funding breakdown and next steps for environmental and sediment testing.