DeSoto drainage replacement to begin this week; completion expected by Nov. 2
Oct 5, 2026
County staff told the Stormwater Board a contractor delayed earlier plans but will start DeSoto drainage replacement this week, with the board expecting completion by Nov. 2 and follow-up at the next meeting.
The full story
The Delaware County Stormwater Board was told on Oct. 5 that the DeSoto drainage replacement project, delayed by contractor scheduling conflicts, is expected to start this week and be complete by about Nov. 2. Dean said the contractor had a backlog of jobs but "he's planning to start that job this week," and staff hopes to report it completed at the next meeting.