Board approves Saddleback elementary GMP and multiple E‑Rate technology contracts
Mar 10, 2026
Mar 10, 2026
Trustees approved a $45.76M Guaranteed Maximum Price to Bartlett Cocke for Elementary #9 (Saddleback) funded from the 2023 bond and awarded several technology contracts (fiber, switches, UPS, cabling) tied to E‑Rate procurement; administration noted potential E‑Rate reimbursements and emphasized value engineering.
The full story
The board approved GMP No. 1 for Elementary No. 9 (Saddleback) with Bartlett Cocke Construction in the amount of $45,756,864.04, to be funded from the 2023 bond program, with work to begin pending permits and a target substantial completion in June 2027.