Council approves wastewater facilities plan that could raise rates about 14.4%

Jul 21, 2026

The council unanimously approved Resolution 26-50, endorsing a phased facilities plan for an outfall relocation that includes contingency for UV disinfection and carries a staff-estimated 14.4% rate increase driven by debt and operational changes.

The full story

The Spring Grove City Council on July 21 approved Resolution 26-50, adopting a facilities plan to relocate the wastewater treatment facility outfall and building a phased plan to accommodate a future UV disinfection system if required. Emma Nollenberger of engineering firm WHKS told the council the phased approach is intended to prevent redoing the facility plan if future limits require UV disinfection.