County engineer outlines schedule for C49 work; bridges reopened
Jul 16, 2024
Pocahontas County Engineer Tate Schmeling said Mathy will begin work July 22 on the C49 project with staged milling, curing and surfacing; Pilot Creek and Hamm bridges are open and crews are working to open the 330th bridge.
The full story
County Engineer Tate Schmeling told the Pocahontas County Board of Supervisors on July 16 that Mathy will begin work on the C49 road project on July 22. Schmeling said the contractor will spend about one to two weeks milling and prepping the roadway, allow two to three weeks for curing, then require another two to three weeks to place the surface; local traffic will be able to get through during work.