Developers detail subsurface stormwater basins, aim to avoid surface ponds

Jan 20, 2026

Engineering team described two subsurface basins (one larger central basin and a smaller shallow basin under guest parking), perforated pipes and a proposed tie-in to a new storm sewer; infiltration testing informed basin siting.

The full story

The applicant's engineer described a stormwater plan that relies on two subsurface basins rather than surface ponds. "We have 2 basins, larger, deeper basin, more central to the site, and then a smaller shallower basin on the southern end of the site," Rich said, explaining that neither basin is proposed to be surface features and that both will tie into a new storm sewer along the frontage and eventually to the existing downstream system.