Washington 10 project: county engineer reports concrete pours and form work underway

Sep 15, 2025

County Engineer Jared Johnson reported on recent progress in the Washington 10 project, including forming, tying and pouring downstream interior barrel sections and plans to complete downstream end barrel and headwall pours this week.

The full story

County Engineer Jared Johnson reported that last week the crew "finished forming and tying reinforcing steel for the downstream interior barrel section, poured the Downstream interior barrel section, stripped wall forms from the downstream interior barrel section," and that this week crews planned to finish tying reinforcing steel and forming the downstream end barrel section and headwall and to pour those sections.