No bidders for Washington 10 project; board moves to construct using county crews

Jul 14, 2025

Ringgold County engineer reported no responsive bidders for the Washington 10 bridge/culvert project and the board moved by resolution July 14 to construct the project using force-account labor and equipment; a road closure was planned to begin July 14.

The full story

Ringgold County Engineer Jared Johnson told supervisors July 14 that hydraulic analysis for the Washington 10 project is complete and that a twin box culvert (twin 10x8x88'-0 RCBC) will satisfy the site’s hydraulic requirements. Johnson reported there were no responsive bidders for the project. The board moved by resolution to construct the project using county (force account) labor and equipment.