Splash pad project delayed after engineers recommend recirculation system, doubling cost

May 16, 2025

A planned splash pad in Barbour County faces delay after CEC recommended switching from a pass‑through design to a recirculation system over concerns about pond capacity and flow; the change would roughly double the $300,000 upfront cost, and staff are seeking additional grants.

The full story

County engineers told commissioners on May 16 that the planned splash pad project needs a design change that will increase cost and delay construction.