Splash pad project delayed after engineers recommend recirculation system, doubling cost

May 16, 2025

A planned splash pad in Barbour County faces delay after CEC recommended switching from a pass‑through design to a recirculation system over concerns about pond capacity and flow; the change would roughly double the $300,000 upfront cost, and staff are seeking additional grants.

The full story

County engineers told commissioners on May 16 that the planned splash pad project needs a design change that will increase cost and delay construction.

Colin McCardle of CEC said the original pass‑through design depended on a direct outlet to an existing pond, but due diligence raised concerns about the pond’s capacity and water flow. CEC recommended a recirculation system, which McCardle said would roughly double the initial $300,000 upfront cost. McCardle reported outreach to multiple grant programs and foundations to secure the extra funding; the commission accepted the update and noted the project is delayed while staff pursues additional funding.

Commissioners thanked McCardle for the update and indicated they would consider the revised budget and funding options before moving forward. No formal vote to cancel or reauthorize funding was recorded in the minutes.