Contractor says King Municipal Operations Center near closeout; occupancy pending lighting fixes
Aug 11, 2026
City contractor reported construction of the King Municipal Operations Center is at punch‑list stage with finishes and furnishings in place and about $20,000 of contingency remaining; occupancy is delayed only by emergency‑lighting/battery backup issues and a contractor inspection scheduled next week.
The full story
Contractor Jack Mulcahy updated council on the King Municipal Operations Center construction timeline and current status. Mulcahy walked through a month‑by‑month photo timeline of demolition, foundation work, structural steel, exterior cladding, and recent interior finishes and furnishing installation.