Council hears Highridge Lane update: culverts installed, backfill drying; completion in 3–4 weeks
Feb 11, 2025
Staff reported box culverts for the Highridge Lane reconstruction have been installed but the required backfill is too wet; the dirt has been piled to dry and headwalls will begin in a few days, with completion estimated in 3–4 weeks depending on weather.
The full story
City staff told the council that box culverts have been installed on Highridge Lane but the backfill dirt is currently too wet to achieve required compaction density. The dirt has been stockpiled to dry, and headwall construction is expected to begin in a few days. The engineer has approved culvert spacing.