Planning Commission recommends Crystal Valley Ranch site plan to Town Council
Oct 8, 2026
The Castle Rock Planning Commission voted 5–0 to recommend the Crystal Valley Ranch site development plan for a 21‑acre single‑family neighborhood to Town Council after applicant and staff presentations and commissioner questions on drainage, buffers and circulation.
The full story
The Castle Rock Planning Commission on Oct. 8 recommended approval of the Crystal Valley Ranch site development plan and will forward that recommendation to Town Council.
Staff planner Carissa Alstrom told the commission the 21‑acre parcel (Filing 14, Lot 1 and part of Tract P) meets the municipal-code criteria and the Crystal Valley Ranch plan amendment; staff recommended the commission recommend approval to council. "Staff analysis ... finds that the site development plan advances the goals of the town's guiding documents," Alstrom said during the hearing.
Applicant Greg Brown, who said he has worked on Crystal Valley Ranch since 1998, presented the site's history and changes made after outreach, including swapping land with the park, increasing the eastern buffer from about 50 feet to roughly 114 feet, removing a through street and adding a cul‑de‑sac and berms to reduce neighborhood impacts. "This project's been almost 30 years in the making," Brown said, asking the commission to recommend approval.
Commissioners questioned circulation and emergency access; the applicant's engineer, James (Jim) Mill, said an EVA with bollards and Knox access will allow fire and emergency vehicles to connect where needed. Commissioners also pressed about grading, view impacts and tree screening; the applicant said larger‑than‑standard trees and a concrete swale will help mitigate runoff and visual impacts.
On drainage, Mill told the commission the design keeps runoff on site and routes it to detention facilities: "It's captured in the existing pipe that actually exists out there today ... and has for..." and that the detention strategy was reanalyzed to meet the town's criteria. Following discussion, a commissioner moved to recommend approval and the commission voted 5–0.
The commission's recommendation goes to Town Council for final decisions and site‑development review, where detailed engineering, landscaping and construction timing will be addressed.