Board reviews drainage progress; Change Order #2 of $6,353.12 discussed
Jul 28, 2026
District engineers reported progress on drainage projects (Turnberry, Palmetto Dunes, Sound III) and discussed Change Order #2 for $6,353.12; Oak Run sodding is delayed by rain and standing water.
The full story
District Engineer Charlie Krebs and Mr. Eric Long briefed the Board on multiple drainage improvement projects under way. Clarke Construction is performing much of the work; Turnberry improvements are nearly complete and Palmetto Dunes and Sound III work is finished with sod replaced. Oak Run (Lakes 8) sodding remains in progress but has been delayed by rain, and standing water was reported where grading and lake-level changes are ongoing.