Promenade (Prudential tract) plan revised: internal ring road and 2,000‑tree commitment highlighted
Dec 16, 2025
Developers showed revised Promenade plans replacing roundabouts with intersections, adding a continuous internal loop road and committing to planting slightly north of 2,000 trees. The application was presented as part of a conditional‑use review for the Prudential tract at 200 Dryden / 2101 Welsh Road.
The full story
Representatives for the Promenade redevelopment (the Prudential tract) returned for a second review and described several plan changes since the zoning stage, including removal of on‑site roundabouts in favor of more traditional intersections and the insertion of a continuous ring road around the central apartment area.
Pete Clellan, presenting the changes, said the internal loop road was the primary substantive difference in the current packet and that the redesign shifts some stacked townhouse clusters and strengthens internal circulation. He added that open‑space, stormwater and landscape plans were updated in the submission.
Clellan also said the design team has tallied tree requirements and will plant “a little bit north of 2,000 trees on the site as a result of this project.” Commissioners asked for clarity on how the ring road would connect to existing access points and whether a dedicated drive aisle would avoid routing external traffic through private parking aisles.
The applicant committed to further internal intersection analyses during land development and to work with the township on access and circulation refinements.
Written with AI from the event video and transcript. Check it against the source ↓