Weatherization work at Warren Community Elementary School complete; final inspection July 27
Jul 23, 2026
Contractor Energy Conservation, Inc. completed weatherization at Warren Community Elementary School in about 2.5 weeks; the town scheduled a final inspection for Aug. 4 for the Shepard Building lift and July 27 for WCES to release the project for fall grant applications. The packet includes as-built photos and a $150,736.83 bill tied to a Green Communities grant.
The full story
Town staff reported the Warren Community Elementary School weatherization project was finished and that the final inspection is scheduled for Monday, July 27, 2026, which will allow the town to proceed with fall applications and grant closeouts. Energy Conservation, Inc. submitted as-built documentation showing air-sealing of doors and windows, framing-penetration sealing above the drop ceiling, installation of a vertical air barrier where needed and insulation on an exposed roof deck area.