Hooker County recommends conditional use for Dismal River Ranch lodge with five conditions

Jun 8, 2023

At a Sept. 20 special meeting the Hooker County Board recommended approval of a conditional‑use application for a 13,200‑sqft lodge and 7,500‑sqft recreation building at Dismal River Ranch, imposing five conditions including Department of Health approvals and road aggregate requirements.

The full story

The Hooker County Board of Commissioners met in a special session Sept. 20 and recommended approval of a conditional‑use application filed by Dismal River Ranch Co., represented telephonically by John Howell.

Howell presented a site plan for a 16.74‑acre tract that included a 13,200‑square‑foot lodge with 12 private bedrooms and bathrooms, a trophy room, dining room, game room and kitchen, plus a 7,500‑square‑foot recreation building with a multipurpose room, bird cleaning room and locker rooms, and a man‑made pond. After reviewing the application and findings of fact, the board recommended approval with conditions:

(a) Applicant must comply with all Nebraska Department of Health requirements for sewer and water; (b) Applicant must comply with any applicable construction and electrical code; (c) Applicant must obtain appropriate building permits prior to commencement of construction; (d) Applicant must convey the 16.74‑acre tract to a separate entity; (e) Applicant shall be responsible for the cost of aggregate on the access road, with the county to build the grade and deliver and apply the gravel.

The motion to recommend the application carried on a 2–0 recorded vote (motion: Thad Emerson; second: Julie Kraye); Vice‑Chair Julie Kraye presided with Chairman Bryan Crisp absent. The minutes record that John Howell participated by phone and presented the plan. The board’s action was a recommendation tied to the conditional‑use process; final zoning or building permits and Department of Health approvals remain prerequisites to construction.

The minutes do not record environmental or traffic studies, nor do they specify timetable or estimated project cost. Road‑improvement responsibility for aggregate was explicitly assigned to the applicant (cost) while the county agreed to build the grade and deliver/apply gravel as a condition of the recommendation. Any final approval or required state permits must be obtained before construction starts.