Engineers: bypass valve not functioning; Phase II waterline project extended

May 12, 2026

McGill Associates reported the bypass valve connection is complete but not operational, paving will wait for asphalt, and final completion was extended with a one-year warranty beginning Dec. 4, 2018 and new target completion Feb. 7, 2019.

The full story

Joseph Meliski of McGill Associates updated the board on the Phase II Waterline Replacement Project and said the connection of the 25/70 Marshall bypass valve with its electrical control panel is in place but "Valve is still not functional." He said final completion had been set for Jan. 7, 2019 but the project received an extension and McGill now lists final completion by Feb. 7, 2019 with a one-year warranty period beginning Dec. 4, 2018.