Board approves change order and final payment for John Koiner reconstruction

Sep 25, 2026

The board considered a change order for the John Koiner reconstruction totaling $42,570.44 (about 19.74%) to extend tile roughly 1,330 feet upstream, approved final payment of $210,860.00, and accepted a reconstruction schedule showing total cost $229,154.50 (assessment $438.98/acre).

The full story

The chair presented a contract change order for the John Koiner reconstruction in the amount of $42,570.44, which he said represents about a 19.74% change (just under the 20% threshold). The primary reason was extending the 12‑inch tile roughly 1,330 feet upstream to give more landowners access; the chair explained the net figure reflects additions offset by planned items that were not completed (red/negative line items). "So that 42,570.44 represents all of the additionals with the subtraction of the things that we didn't do that we had planned on," he said.

Free newsletter

Sign up to keep reading.

Your free newsletter brings you what your city council, county, and school board discussed and decided.

or
Already have an account? Sign in