Council OKs $367,726 contingency increase for Innovation Center utilities work
Oct 14, 2026
Oct 14, 2026
Council approved amendment No.1 to the R & R Pacific Construction contract to add a 15% contingency ($367,726) after contractors encountered unanticipated underground utilities and high groundwater during excavation for the Innovation Center infrastructure; new total authorized contract is $3,186,958.
The full story
The council on Oct. 13 approved an amendment to the construction contract for the Innovation Center infrastructure project after staff reported unforeseen subsurface conditions required additional work.