Jury hears update on Zydeco Solar Project; site work could start in October

Sep 8, 2025

Recurrent Energy told the Evangeline Parish Police Jury that Zydeco Solar design is about 90% complete, permitting is in final review, and early site work could begin Oct. 6 with construction targeted for early November 2025.

The full story

Recurrent Energy updated the Evangeline Parish Police Jury Sept. 8 on the Zydeco Solar Project development timeline and permitting status. The company reported the design is about 90% complete and that the building permit was in final review with the Rapides Area Planning Commission. Parish road entrance and boring permits were to be submitted to the Public Works Director by Sept. 12.