Local mitigation work proceeds: CUSP completes acres, slash site preps reopening; CWPP rewrite underway

Jan 15, 2025

CUSP reported completion of 15 acres on the Stedman property and plans to finish delayed Catamount work; the slash site processed 70 more loads in 2024 and is slated to reopen in May 2025. The county CWPP rewrite is 50–60% complete and awaiting GIS and chief feedback.

The full story

John Geerdes reported progress on Community Urban and Structural Protection (CUSP) mitigation projects: 15 acres were completed on the Stedman property near Catamount, Green Mountain Falls and Crystal Peak, and a 20‑acre project at Catamount originally planned for 2024 was delayed by snow. Geerdes said crews hope to complete the 2024 and 2025 planned acres in the upcoming season.