Board hears capital projects update; project manager keeps June 30 completion target
Mar 26, 2026
District presenters told the board that additions are ~75% complete and alterations ~95% complete; contractors gave a June 15 estimate but the project manager retained a conservative June 30 target and noted $3.7 million of remaining scope.
The full story
The Eastport‑South Manor Board of Education received a monthly capital projects update that detailed progress on Phase 2 school additions and renovations and the district’s remaining work to close out several elementary projects. Presenters said masonry and structural steel are largely complete, interior HVAC/electrical rough‑ins are in place in the library and labs, AV systems have been installed in gyms, and finish work is under way in the new dance studio and fitness spaces.
Sign up to keep reading.
Your free newsletter brings you what your city council, county, and school board discussed and decided.
Keep reading for free
Create a free account to finish this story and see the video, transcript and key details.
Continue with GoogleContinue with emailAlready have an account? Log in →