IFT reports control-panel installation and temporary sludge-tank repair

Apr 20, 2026

IFT contractor Austin Eder reported a control panel was installed and conduit work begun; a VFD will be relocated to the panel. The IFT crew also put a tarp on a sludge tank as a temporary repair while a replacement is sought.

The full story

IFT representative Austin Eder reported that a control panel has been installed and that crew members are starting to run conduit for electrical lines; the variable-frequency drive (VFD) will be moved to the new control panel. The minutes record these as active, in-progress operational tasks.