Construction manager: 12 days between final docs and bid issue is typical

Oct 14, 2026

A council member questioned the 12-day period between 100% document completion and issuing bids; Michael Stein, the construction manager, said the team compiles a 95% set earlier and the final 12 days are typically used to assemble the bid package, so he had no concerns.

The full story

A council member expressed concern about the roughly 12 days scheduled between completion of 100% construction documents and issuing the bid package, asking whether that left enough time for review and confidence in the documents.