Council hears progress reports on streets, subdivision and parks projects
Nov 13, 2024
Administrator Francis reported completion of asphalt work in Rosecomb Estates Phase II, final paving of N. East St., curb and sidewalk replacement on S. Center St., ongoing recloser programming, biosolids land application, and that Ward Park pool finished the season with a $17,202.83 operating loss.
The full story
Village Administrator Francis gave an extended administrative report covering multiple infrastructure and operations items. He said "The asphalt work has been completed in the Rosecomb Estates Phase II residential subdivision" and that final grading and property pins remain before a formal acceptance recommendation. He also reported that the N. East St. Reconstruction Project finished with asphalt placed, that PAB Construction began curb and sidewalk replacement on S. Center St. (project cost estimated at $20,626.00), and that electrical crews installed mid‑span poles to re‑route a three‑phase feed away from a CSX right‑of‑way to improve reliability.