Capital program update: Central Valley vestibule completion, Pine Tree and tennis‑court work progress
Apr 9, 2026
Patrick Cahill said phase 1 construction is in punch‑list stage, SED substantial‑completion filings are pending to unlock state aid, Pine Tree and tennis‑court work is underway and a draft feasibility for zero‑emission buses is nearly complete.
The full story
Patrick Cahill provided a multi‑phase capital program update, describing phase 1 (boiler replacements, Central Valley security vestibule, education center renovations) as in punch‑list work and noting the need to file substantial‑completion paperwork and final cost reports (FCRs) with the State Education Department (SED) to trigger state‑aid eligibility. Cahill told the board "Tonight on the agenda, we had substantial completion for the Central Valley Security Vestibule documentation" and said approval would enable the final cost report filing.
Sign up to keep reading.
Your free newsletter brings you what your city council, county, and school board discussed and decided.
Keep reading for free
Create a free account to finish this story and see the video, transcript and key details.
Continue with GoogleContinue with emailAlready have an account? Log in →