CDD updates long-range plan: gatehouse and monument replacements, $291,500 backup well nearing completion

Apr 28, 2026

The Board reviewed a revised long range plan that includes monument replacements (estimated $250,000), gatehouse renovations (FY2026 $615,775; FY2027 $407,240), and a near-complete backup irrigation well costing $291,500 expected to become the CDD's primary well.

The full story

Eric Long distributed and reviewed a revised Long Range Plan and provided cost estimates and schedule updates. He said the Traffic Calming Project cost $26,739 and that the backup irrigation well cost $291,500 is near completion; he expects the current pump to be installed and operating within weeks and said the new well is anticipated to become the CDD's primary well while the existing well will be secondary.