Board reviews drainage progress, change order #2 and contingency usage

Jul 28, 2026

Engineers reported drainage work progressing across multiple neighborhoods; Change Order #2 for $6,353.12 was discussed and staff noted an original 15% contingency (~$112,000) with some roof drain funds rolled into contingency.

The full story

District Engineer Charlie Krebs and Eric Long updated the board on drainage improvements, noting Clarke Construction performed much of the work. Turnberry improvements were described as almost complete; Palmetto Dunes and Sound III work including sodding and tree installation were reported finished. Oak Run in Lakes 8 is being sodded but progress is delayed by rain and standing water; silt fences are in place.

Free newsletter

Sign up to keep reading.

Your free newsletter brings you what your city council, county, and school board discussed and decided.

or
Already have an account? Sign in