Commissioners accept $85,340 deduction from contingency on Rattlesnake wastewater project; contract total unchanged
Sep 2, 2025
Sep 2, 2025
Fayette County commissioners voted Sept. 2 to accept Contract Change Order #7 for the Rattlesnake Wastewater Treatment Plant, deducting $85,340 from the embedded owner contingency while leaving the $18,289,538 guaranteed maximum price unchanged.
The full story
Fayette County Commissioners on Sept. 2 approved Contract Change Order #7 with Peterson Construction for the Rattlesnake Wastewater Treatment Plant, reducing the embedded owner contingency by $85,340 while keeping the contract amount at $18,289,538.